ALT The Texas Commission on Environmental Quality will hold a public hearing at 7 p.m. April 15 in Portland, Texas, on a draft air operating permit proposed for the expansion of the Corpus Christi LNG terminal, which has been exporting natural gas since 2018. The expansion will significantly increase the terminal's capacity to liquify natural gas for export.

ALT Texas LNG seeks 5-year delay on South Texas terminal, citing legal battles Texas LNG a company planning a liquified natural gas (LNG) export terminal along the Brownsville Ship Channel on the southern tip of Texas, is seeking a delay until November 2029 to finish building the facility.

ALT In a May 24, 2024, filing to the Federal Energy Regulatory Commission (FERC), Texas LNG cited litigation over the project’s FERC authorization and its state-issued air permit by the Sierra Club, the City of Port Isabel, and community groups. If built, the facility will be capable of exporting up to 4 million tons of LNG per year.