ALT One of the most common mistakes I see people make when looking at data is incorrectly using an overly simplified model. A specific variant of this that has derailed the majority of work roadmaps I've looked at is treating people as interchangeable, as if it doesn't matter who is doing what, as if individuals don't matter. Individuals matter. A pattern I've repeatedly seen during the roadmap creation and review process is that people will plan out the next few quarters of work and then assign some number of people to it, one person for one quarter to a project, two people for three quarters to another, etc. Nominally, this process enables teams to understand what other teams are doing and plan appropriately. I've never worked in an organization where this actually worked, where this actually enabled teams to effectively execute with dependencies on other teams. What I've seen happen instead is, when work starts on the projects, people will ask who's working the project and then wi...