Scheduled power interruption in Camiguin and parts of Misamis Oriental on Sunday, 22 November 2026
Time: 7:00AM – 5:00PM
Affected: CAMELCO and parts of MORESCO 2
Reason: Maintenance activities along Jasaan-Kinoguitan 69kV Line
Specific areas are determined by the affected electric cooperatives. NGCP will exert all efforts to restore power earlier or as scheduled.
#NGCP
1
130
Scheduled power interruption affecting parts of Lanao del Sur, 22 November 2026.
Time: 7:00AM-4:00PM
Affected: LASURECO
Reason: maintenance activities along Basak-Malabang 69kV line segment.
Specific affected areas are determined by the electric cooperative. NGCP will exert all efforts to restore power earlier or as scheduled.
#NGCP
201
Fully restored power transmission service in parts of Lanao del Sur, 18 November 2026, 2:15PM.
Affected: LASURECO
Restored: Basak-Malabang 69kV line segment
Reason: the line outage at 9:27PM on 17 November 2026, remains under investigation to determine its root cause.
Prior to full restoration, power transmission service was partially restored up to the Bacolod-Kalawi areas at 9:44PM on 17 November 2026, and further extended to the Ganassi areas at 8:10AM on 18 November 2026.
NGCP and LASURECO line personnel worked jointly in conducting line inspections and restoration activities, resulting in the full restoration of power transmission service.
#NGCP
1
204
Restored power transmission service in parts of Camarines Sur Province today, 18 November 2025 at 5:26PM
Affected: CASURECO III (Bula, Nabua, and Iriga Substations)
Reason: Shutdown of Naga-Iriga 69kV Line to facilitate maintenance activities along the line
We appreciate your patience and understanding during the power interruption.
#NGCP
1
163
𝐌𝐀𝐍𝐀𝐓𝐈𝐋𝐈𝐍𝐆 𝐋𝐈𝐆𝐓𝐀𝐒
Huwag magtayo ng bahay o anumang istruktura sa ilalim ng mga linya ng kuryente.
Ang pagtatayo ng mga bahay o anumang istruktura sa ilalim ng mga linya ng kuryente ay labis na mapanganib.
Bukod sa maaari itong magdulot ng sunog o pagkakuryente, maaari rin itong makaapekto sa maayos na pagdaloy ng kuryente sa linya na pwedeng magdulot ng mga power interruptions.
Hangad namin ang inyong kaligtasan at kapakanan.
#NGCP
#ngcpsafety
1
211
Scheduled power interruption in parts of Albay on Thursday, 19 November 2026
Time: 6::00AM - 8:00AM
Affected: ALECO (Salvacion Substation and Sta. Misericordia Feeder 1 and Feeder 2)
Reason: Shutdown of Daraga-Sto. Domingo 69kV Line as per request of ALECO to facilitate tapping of their new Daraga (Cullat) Load-End Substation
Specific areas are determined by the affected electric cooperative. NGCP will exert all efforts to restore power earlier or as scheduled.
1
216
Scheduled power interruption in parts of Maguindanao del Sur and Manguindanao del Norte on Sunday, 22 November 2026.
Time: 06:00 AM - 5:00 PM
Affected:
MAGELCO (Talayan Substation)
Time: 06:00 AM - 06:10 AM & 04:50 PM - 05:00 PM
Affected: MAGELCO (Rajah Silongan Kudarat & Salbu Substations)
Reason: Shutdown of Dukay -Talayan 69kV line section to facilitate line repairs
Brief power interruptions are due to isolation and normalization of Salbu-Talayan 69kV line section before and after the scheduled repairs.
Specific affected areas are determined by the electric cooperative. NGCP will exert all efforts to restore power earlier or as scheduled.
#NGCP
205
Scheduled maintenance activities in parts of Cagayan and Kalinga on Saturday, 21 November 2026
Time: 6:15AM – 6:15PM
Affected: Parts of CAGELCO I (Carig, Caritan, Solana and Piat Substations) and KAELCO (Tabuk Substation)
Reason: Upgrading activities at Tuguegarao Substation.
Specific areas are determined by the affected electric cooperatives. NGCP will exert all efforts to restore power earlier or as scheduled.
#NGCP
1
269
Scheduled power interruption in parts of Isabela on Saturday, 21 November 2026
Time: 8:00AM – 12:00NN
Affected: ISELCO I (Reina Mercedes and District 1 Substations) and ISELCO II (Ilagan, Naguilian and San Mariano Substations)
Reason: Implementation of corrective and maintenance activities at Gamu Substation and along Gamu–Cauayan 69kV Line.
Time: 8:00AM – 5:00PM
Affected: ISELCO II (Ilagan – Burgos 13.8kV line)
Reason: Corrective maintenance works at Ilagan Substation
Specific areas are determined by the affected electric cooperatives. NGCP will exert all efforts to restore power earlier or as scheduled.
#NGCP