Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)Photo by The Base Bid (@TheBaseBid)
GSA PBS is asking industry about a nationwide construction IDIQ: potentially 40–50 awards, seven zones, a scorecard per zone. Responses due Oct. 5. Also: 134 deadlines, a $373.5M NAVFAC barracks award, and 1,157 construction notices government-wide. thebasebid.com/issues/2026-0…
129
The Five-Minute Check: a government delay you have not put in writing is costing you money you will not get back. On a federal construction contract, FAR 52.242-14 allows no claim for costs you incurred more than 20 days before your written notice.
1
1
The check: list what you are waiting on the government for. Next to each, write the date it started costing you money. Anything past 20 days with no written notice, send the notice today. It reaches back 20 days and no further. acquisition.gov/far/52.242-1…
1
Three federal construction vehicles turned up this week. Only one of them is taking proposals.
1
4
GSA PBS: DOT office renovation at the Denney Federal Building, Lincoln NE. Open only to holders of the GSA Heartland Small Business IDIQ MATOC for Nebraska. Offers due Thu 17 Dec 2026, 1:00 p.m. CT.
1
2
Did You Know? On a federal construction job the survey layout is your expense. And if your crew destroys a government bench mark before you are authorized to remove it, the contracting officer can replace it and deduct the cost from what you are owed.
1
Our read: layout is a line in your estimate, not a government service. Check Section I for 52.236-17, then check the drawings for the base lines and bench marks your layout starts from.
1
Open now, two jobs that are mostly lines and grades. Canandaigua VA Medical Center seal and stripe, 36C24227B0005, due Dec 3, 11:00 a.m. ET. Dugway Proving Ground paving IDIQ, W911S6-27-B-A001, bid opening Nov 24, 1:00 p.m. MT. Clause: acquisition.gov/far/52.236-1…
1
Did You Know? The government can award another construction contract at or near your site while you are working there. Your contract requires you to cooperate and adapt your schedule to it. FAR 52.236-8, Other Contracts.
1
2
This is not hypothetical. The Army Corps of Engineers Baltimore District has two separate small business sources sought open for construction at Fort Meade, Maryland, both closing 4 December at 11:00 a.m. Eastern. sam.gov/opp/a6ae2225a1bd4be7…
1
What to check: read Section I of the solicitation for 52.236-8, then ask at the site visit what other work is planned at or near the site during your period of performance. Coordination you cannot see is coordination you have not priced. acquisition.gov/far/52.236-8