5 days of construction complete! Take a look at our new pictures: solardecathlon.illinois.edu/
Construction in D.C. has begun. Take a look at our photo gallery for assembly updates: solardecathlon.illinois.edu/
The Re_home is leaving Illinois' campus today to begin its trip to DC. Follow us at the Solar Decathlon starting September 13.
1
3
Marmoleum floor installation has begun. Next step- assembly of kitchen cabinetry.
The Re_home's cedar plank siding should be completed this week! http://twitpic.com/5oejlj
PV installation starts today!
Cedar planks for the Re_home's siding were all painted in one day thanks to a great team effort!
Check out photos of the Re_home being delivered on campus! http://www.flickr.com/photos/58744079@N03/sets/72157626628735195/
http://www.dailyillini.com/index.php/multimedia/27894
The house was successfully delivered to campus today. Stay tuned for updates as students continue construction throughout the summer.
The Re_home is being delivered to campus this morning between 7:30 and 8:30. Come to the site just southeast of the south quad!
Floor construction progress from Friday http://flic.kr/p/9A6vwo
Floor and walls are built. Walls will be set in place tomorrow!
Construction started at Homeway Homes on Friday! Pictures will be posted soon.
Check out the latest progress on the Re_home! http://vimeo.com/22246902
Visit the Re_home display at the Museum of Science and Industry! http://www.msichicago.org/whats-here/events/go-green-money-smart-week/
Check out the Re_home project at Go Green on Green Street today by the Alma Mater!
Vote for the Solar Decathlon! http://www.treehugger.com/galleries/2011/03/best-of-green-design-architecture.php?page=5
The new competition location was announced!! Check it out: http://www.solardecathlon.gov/blog/archives/731
Team Illinois successfully resubmitted the Design Development deliverable to the DOE today!