INFRASTRUCTURE PROGRESS UPDATE Work on the rigid pavement for the Karachi BRT Red Line Corridor at the NIPA Hydrant area is currently in process. #KarachiBRTRedLine #TransKarachi #ProgressUpdate #UniversityRoadKarachi #BRTRedLine
3
3
100
INFRASTRUCTURE PROGRESS UPDATE The University of Karachi (KU) Elevated U-Turn 2 for mixed traffic is nearing completion, with the asphalt wearing course completed and expansion joint works currently underway. #KarachiBRTRedLine #TransKarachi #UniversityRoad #KUElevatedUTurn
1
119
OFFICIAL STATEMENT Gas Leakage Identified and Rectified During BRT Red Line Project Work on University Road; Gas Supply Restored #TransKarachi #KarachiBRTRedLine #GasPipeline #UniversityRoad #Karachi
1
130
MIXED TRAFFIC LANE PROGRESS UPDATE The Mixed Traffic Lanes along the Karachi BRT Red Line Corridor from Malir Halt to Numaish are almost complete. #KarachiBRTRedLine #TransKarachi #UniversityRoad #KBRT #Karachi
3
1
1
14
1,485
SERVICE LANE NOW OPEN The service lane on the left side of the road from King's Cottages to Mosamiyat is now open for traffic. #TrafficAdvisory #KarachiBRTRedLine #KBRT #TransKarachi #Karachi
3
143
SERVICE LANE NOW OPEN The service lane on the left side of the road from Tank Chowk to Airport Signal is open for traffic. #TrafficAdvisory #KarachiBRTRedLine #KBRT #TransKarachi #Karachi
112
INFRASTRUCTURE PROGRESS UPDATE Leg 1 of Level 1 of the Safoora Flyover is nearing completion. Meanwhile, work on Leg 2 of Level 1 as well as Level 2 of the flyover is also progressing steadily. #KarachiBRTRedLine #TransKarachi #ProgressUpdate #SafooraFlyover #Karachi
80
INFRASTRUCTURE PROGRESS UPDATE The grey structure for the Karachi BRT Red Line Tipu Sultan Station is now 100% complete. #KarachiBRTRedLine #TransKarachi #ProgressUpdate #KBRT #Karachi
1
94
INFRASTRUCTURE PROGRESS UPDATE Foundational works on the Malir Cantt Station for the Karachi BRT Red Line have reached 100% completion. #KarachiBRTRedLine #TransKarachi #KBRT #MalirCanttStation #Karachi
1
89
INVITATION FOR BIDS TransKarachi is inviting bids for the procurement of the construction of the Underground Staging Facility under KGA at Numaish. For further details, visit: transkarachi.pk/bids-and-ten…. #TransKarachi #KarachiBRTRedLine #KBRT #InvitationforBids #Karachi
71
Asphalt laying work is ongoing on a section of the right side of the road from Safoora Chowrangi to Mosamiyat (Pizza Max to Ahmed Hanif Rajput Pakwan House). Traffic will be diverted. #TrafficAdvisory #KarachiBRTRedLine #KBRT #TransKarachi #Karachi
89
INFRASTRUCTURE PROGRESS UPDATE The Tipu Sultan Underpass, an infrastructural element of the Karachi BRT Red Line Project located near Checkpost 6, Malir Link Road to Super Highway, has reached 100% completion. #KarachiBRTRedLine #TransKarachi #TipuSultanUnderpass #Karachi
1
3
135
TransKarachi's Official Statement on Incident Near Bait-ul-Mukarram #TransKarachi #KarachiBRTRedLine #KBRT #Karachi #Pakistan
82
Inauguration of the Mosamiyat Flyover, held on Sep 27, 2026, in the distinguished presence of Sr. Minister Sharjeel Memon, Provincial Minister of Sindh for Local Government Saeed Ghani, Secretary TMTD Asad Zamin, CEO TransKarachi Zubair Ahmed, & officials from FWO & TransKarachi
1
1
287
TransKarachi is pleased to announce that the Mosamiyat Flyover, a key component of the Karachi BRT Red Line project, has been inaugurated today, September 27, 2026. #TransKarachi #KarachiBRTRedLine #KBRT #MosamiyatFlyover #Karachi #Pakistan
2
1
3
6
4,878
INFRASTRUCTURE PROGRESS UPDATE The grey structure of the Race Course Station for the Karachi BRT Red Line has reached 100% completion. #KarachiBRTRedLine #TransKarachi #KBRT #RaceCourseStation #Karachi
1
200
The right side of the road from Tank Chowk to Airport Signal will remain closed from Thursday, Sep 24 to Saturday, Sep 26, due to ongoing asphalt work. Traffic will be diverted. The road will open for traffic on Sunday, Sep 27. #KarachiBRTRedLine #KBRT #TransKarachi #Karachi
121