ALT Dark Delivery Dates Research card titled "29 of 79 past-due delivery promises slipped." Subtitle: Promised dates, checked against the companies' later SEC filings. Left panel: 29/79 slipped, 36.7%; delivered late 21; moved later 8; median for late ones 62 days; range for late ones 1 to 366 days. Right panel: a grid of 79 cells, one per past-due promise, with 21 red cells for delivered late and 8 gold cells for moved later. Footer: Source: companies' own SEC filings, each promise checked against later filings. Not investment advice. deliverydates.substack.com. Somebody should check. We did.

ALT Cream diagram from Delivery Dates Research, as of Nov. 16, 2026, titled Conditional Until December, with the kicker ERCOT's Texas large-load dates, and the conditional Batch Zero classifications three companies we track report. A timeline runs from Aug. 3, 2026 (filled: Governor's directive. After it, ERCOT paused approvals to energize data centers, 75 MW+) through Sep. 3, 2026 (filled: Conditional classifications sent to transmission service providers), Nov. 5, 2026 (filled: Update to PUCT: second-round RFIs; review due this month), Dec. 10, 2026 (open: Verification and community impact reports due at PUCT), and Dec. 17, 2026 (open: PUCT open meeting listed after the reports). A note reads: ERCOT: final inclusion or exclusion "provided in December". Legend: Filled: happened. Open: scheduled. Spacing not to scale. Below, a table of what the companies report for Texas sites: Cipher Digital, Colchis, 1 GW, Conditional base load, 8-K Ex. 99.1, Nov. 2, 2026; Cipher Digital, Additional pipe

ALT Light chart titled "Still Subject to Verification," dated Nov. 17, 2026, comparing Soluna's September 8 and September 14 8-K quotes on conditional Base Load classifications at the 166 MW Kati campus and the 100 MW Dorothy campus with the November 16 10-Q confirmation that those classifications remain subject to ERCOT's verification, and the same day's release line that an additional 50 MW request at Dorothy is under study.

ALT Light chart titled "Still Subject to Verification," dated Nov. 17, 2026, comparing Soluna's September 8 and September 14 8-K quotes on conditional Base Load classifications at the 166 MW Kati campus and the 100 MW Dorothy campus with the November 16 10-Q confirmation that those classifications remain subject to ERCOT's verification, and the same day's release line that an additional 50 MW request at Dorothy is under study.

ALT Chart titled The CB-4 dates, filing by filing, whose four 8-K columns, Oct. 6, 2025 through Nov. 6, 2026, show TeraWulf's CB-4 delivery and rent window moving from an assumed 3Q26 lease start to the second half of 2026, then narrowing to Q4 Nov–Dec 2026, with energization expected Q3 2026 in February and no later filing saying CB-4 was energized, and whose separate 10-Q row below reads remaining Fluidstack leases Q4 2026 and early 2027 and does not say CB-4 was delivered or energized.

ALT Chart titled The CB-4 dates, filing by filing, whose four 8-K columns, Oct. 6, 2025 through Nov. 6, 2026, show TeraWulf's CB-4 delivery and rent window moving from an assumed 3Q26 lease start to the second half of 2026, then narrowing to Q4 Nov–Dec 2026, with energization expected Q3 2026 in February and no later filing saying CB-4 was energized, and whose separate 10-Q row below reads remaining Fluidstack leases Q4 2026 and early 2027 and does not say CB-4 was delivered or energized.