Delivery Dates Research (@DDResearchDesk) header
Delivery Dates Research (@DDResearchDesk) profile picture

We check data-center delivery dates against SEC filings. 29 of 79 past-due promises slipped. AI-assisted, filing-checked. https://xitter.cf/t.co/G7fCPQjnbF

Joined October 2026
Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)Photo by Delivery Dates Research (@DDResearchDesk)
29 of 79 past-due delivery promises slipped: 21 delivered late, 8 moved later. Late ones ran a median 62 days. Each promise sits beside the company's later SEC filing. Free summary: deliverydatesresearch.com/ $SLNH $BTDR $WULF
1
1
159
Power hour. Last hour before the bell. Leading our covered universe today: $HUT, up 1.11% as of 12:03 PM PT. $IREN led today's volume. The tape moves. The calendar decides. Hut 8's Nov. 4, 2026 8-K (Exhibit 99.1), on its Beacon Point campus: "signing a second 352 MW IT lease with the Phase 1 tenant (the “Phase 2 lease”)." Next dated promise: "Advanced the buildout of Beacon Point, with initial data hall delivery targeted for Q3 2027 at Phase 1 and Q2 2028 at Phase 2." Our ledger: 29 of 79 past-due promises we've checked slipped (21 late, 8 moved). Hut 8 is not in that 79. Not investment advice. Dates from SEC filings. Research assisted by AI, checked against SEC filings. Delivery Dates Research reads public filings and tracks what companies said about timing. Nothing here is investment advice. #PowerHour #SECfilings
79
Texas grid reports are due December 10. Three companies we track say their Texas sites hold conditional Batch Zero classifications. ERCOT says final decisions come in December. A grid classification is not a delivery date. deliverydates.substack.com/p… $CIFR $IREN $SLNH
202
Longest delay on our ledger: 366 days. Applied Digital 8-K, July 18, 2022: "The Company is planning to energize the Garden City facility late in the third calendar quarter of 2022." 8-K, Jan. 16, 2024: "Our Garden City facility was energized in October" October 2023. $APLD
50
Soluna's Q3 10-Q, filed November 16: 166 MW at Kati and 100 MW at Dorothy remain conditional Base Load in ERCOT's Batch Zero process. "These classifications remain subject to ERCOT's verification." A grid classification is not a delivery date. sec.gov/Archives/edgar/data/… $SLNH
1
1
121
The longer write-ups, with the filings linked, go out free on Substack: deliverydates.substack.com/ $SLNH
76
TeraWulf has dated Lake Mariner's CB-4 three ways in its SEC filings. TeraWulf's October 2025 investor presentation assumed "CB-4 lease commencement in 3Q26". From Exhibit 99.1 of the Aug. 5, 2026 8-K: "The first CB-4 data hall has entered commissioning, with phased delivery and rent commencement expected during the second half of 2026, while CB-5 remains targeted to begin phased delivery in early 2027." From Exhibit 99.1 of the Nov. 6, 2026 8-K: "CB-4 remains on track for phased delivery and rent commencement during the fourth quarter." The same 8-K's Exhibit 99.2 says "CB-4: 168 MW phased Nov–Dec 2026". That window sits inside the second half named in August. We are not treating the November 8-K as a further move. TeraWulf's Q3 2026 10-Q (acc 0001628280-26-071671), accepted later the same day, says the remaining Fluidstack HPC Leases are "expected to commence in the fourth quarter of 2026 and in early 2027", with "commencement on a data hall-by-data hall basis". A separate sentence on the Akela Fluidstack Leases says remaining capacity is "scheduled for phased commencement during the fourth quarter of 2026 and the first half of 2027". As of September 30, 2026, Lake Mariner "had 102 MW of energized critical IT HPC capacity". A further line says "approximately 500 MW of aggregate gross capacity expected to be energized by early 2027". The 10-Q does not say CB-4 was delivered or energized, and it does not say which halls are in the early-2027 group. CB-4 appears only as a lease commencement date term. From Exhibit 99.1 of the Feb. 26, 2026 8-K: "CB4 (168 MW) – Energization expected Q3 2026". We have not found a later filing that says CB-4 was energized. Commissioning is not energization. We will check these dates against later filings, and we will re-check when a CB-4 commencement filing or 8-K appears. We already count the August change as a move later. We are not counting the November 8-K as a further move. We are not changing our count. $WULF Delivery Dates Research reads public filings and tracks what companies said about timing. Nothing here is investment advice. Dates from SEC filings. Research assisted by AI, checked against SEC filings.
1
28
The full write-up, filing by filing, with a link to each SEC filing quoted: deliverydates.substack.com/p…
3
Matt Estes, who writes Explaining the Grid on Substack, on what we do (Nov. 4): "It provides both the start date included in an announcement ... and subsequent projected start dates in public companies' financial statements filed at the SEC ..." The calendar is undefeated. Research assisted by AI, checked against SEC filings.
2
1
99
At the close. Leading our covered universe today: $CORZ, up 0.97% at the 1:00 PM PT close (11 of 12 names were down). $IREN led today's volume. The tape moves. The calendar decides. Core Scientific's Nov. 5, 2026 10-Q: 485 MW billing vs 590 MW leased to CoreWeave, "the remaining 105 MW in various stages of construction and commissioning." Next dated promise: the AMD leases (about 530 MW, signed July 2026) "are expected to commence in phases beginning in 2027." Our ledger: 29 of 79 past-due promises we've checked slipped (21 late, 8 moved). Core Scientific is not in that 79. Not investment advice. Dates from SEC filings. Delivery Dates Research reads public filings and tracks what companies said about timing. Nothing here is investment advice. #SECfilings
142
Leased Is Not Billing Core Scientific's results tables list 225, 395 and 485 billing MW. Its 10-Q puts 485 against 590 MW leased, with 105 MW in construction and commissioning. TeraWulf counts the same stages at Lake Mariner and in Kentucky. deliverydates.substack.com/p… $CORZ $WULF
1
120
The calendar is undefeated. We compare the delivery dates data-center operators promise with what their later SEC filings report. 29 of 79 past-due promises slipped (36.7%): 21 delivered late, 8 moved later. Late ones ran a median 62 days. $SLNH $BTDR $WULF
302
A correction. 29 of 79 past-due promises slipped (36.7%): 21 delivered late, 8 moved later. Median 62 days late, range 1–366. Some Oct. 26–27 posts still show 22 of 79 or 27 of 79. This post corrects them. We now say “delivered on time.” deliverydates.substack.com/p…
20
$RIOT Riot’s Nov. 4, 2026 8-K, Exhibit 99.1, sets this Corsicana schedule. We will check those three dates against later filings. sec.gov/Archives/edgar/data/…
108
$IREN Horizon 1 "...delivered to and accepted by Microsoft in August 2026...," the 10-Q says. The 10-Q does not name Horizons 2-4 in the moved-date sentence. We are not counting this as a Horizons 2-4 slip until a filing ties it to them. sec.gov/Archives/edgar/data/…
1
168
We have 5 gift subscriptions to Delivery Dates Research for readers who follow data-center and miner build schedules. Each is a free month of the paid tier once paid posts start. Every post is free to read now. DM us the email and we'll send it. First five who ask.
7
Delivery Dates Research retweeted
Replying to @blockspace
We remember Ben saying 3 deals by the end of the year…that’s the whole point of what we do. Promises kept and promises slipped… Ben slipped
1
1
22
We're updating one of our own IREN rows. Childress Phase 6 had later word in IREN's filings than we had logged. Jan 21, 2025: "the final 100MW (Phase 6) at Childress, completing the full 750MW data center project by the end of 2025" Feb 6, 2025: "construction of final 400MW underway (Phase 4 - 6)" May 14, 2025: "Pausing mining expansion at 50 EH/s, previously 52 EH/s". The notes for that slide name miners for a "25MW Childress Phase 6 expansion". We've parked the row pending a label. We're not labeling it late, delivered, or dropped. sec.gov/Archives/edgar/data/… sec.gov/Archives/edgar/data/… sec.gov/Archives/edgar/data/…
16