29 houses for Phase 1 now complete. Phase 2 works ongoing with the last timber kit currently being erected.
Service connections commenced to plots. eg gas & electric + meters. Kitchens due for delivery & installation. Painter works commenced.
Ventilation, sprinkler and plumbing works commenced. Brick and block superstructure works commenced Gindera Rd main cold water works ongoing
All going well, Scottish Water main cold water works to commence Mon 10th Sept. for 5 days. Run from Rosehill Cottages to middle Gindera Rd.
Floor slab insulation and screed works commenced on site. Warmcell wall insulation works ongoing. Tobermore retaining wall works ongoing.
Timber kit erection works now well under way. Roof tiling works and solar panel installation now commenced.
Footpath from Gindera Rd to Broomfield Rd closed temporarily due to services work and excavations. Will be reinstated as soon as is possible
Timber kit erection works commenced with Plot 1
Mains Cold Water services installation commenced
Tar road base in place
#BCLFutureWorks - Erect Timber Kits. Utilities Services Installation.
#BCLCurrentWorks - Sewer works on main roads within site boundary. Plot drainage and concrete foundation works.