There's a lot of ground to cover when you're building a Moon Base.
During the first phase of @NASAMoonBase development, robotic rovers will gather new details about the lunar South Pole region, while lunar terrain vehicles will extend the reach of each Artemis mission.
Andre🇨🇮 retweeted
Le groupe pour la réception de Barcelone ! 🗒️
#UCL
Andre🇨🇮 retweeted
Was waiting for Jared to post something gigaquotable but this was too funny not to share
Wait, I was told SpaceX wasn’t even working on HLS. 😂 Don’t worry, once the hardware shows up, it’ll be “unrealistic,” the dates will be “fake,” and HLS will “never happen.” The goalposts are ready.
NASA has given us lots of information of Starship HLS, this is a very real vehicle with tons of work being put into it.
SpaceX has nearly completed HLS Cabin One, a 1:1 matching of the real flight cabin for astronaut testing operations. SpaceX will likely show off the hardware for it within 2 months (this month is a high contender)
The Artemis III Starship will have its docking system integrated by the end of the year and have its emulator and communications delievered in early 2027, this Ship will perform cryo and static fire tests in Q2 2027.
HLS landing legs to be demonstrated in Q2 of 2027 along with Cabin One's airlock.
Orbital refueling test of Starship set for Q1 of 2027!
Pad LC-37 to be ready in Q1 2027 (already was known)
First Cape and V3 booster reflight in Q4 of 2026, this may mean 3 more flights this year?
Tank pressurization upgrades to SuperHeavy (?)
Uncrewed HLS lannding mission in Q4 2027 with tankers.
Andre🇨🇮 retweeted
Update on the HLS provider timelines from NASA
Short Overview:
Still targeting early 2028 for Artemis 4 and late 2028 for Artemis 5.
Starship cargo lander expected in 2032 and Mk2 cargo lander in 2033.
NASA provided an image of the CONOPS for Artemis 3 which is currently targeting NET Q3 2027.
Starship uncrewed landing demo still targeting NET Q4 2027. Blue Origin uncrewed Mk2 landing demo NET Q1 2028.
Starship Milestones:
First cape flight in Q4 2026 (currently NET Dec 10th). Completed HLS "Cabin 1" in Q4 2026 (ground testing cabin). This will have operations testing in Q1 2027 and airlock demonstrations in Q2.
Prop demo in Q1 2027, first launch from LC-37 also in 2027 - I personally believe 37a will be ready in Q2 or Q3.
Tank presurizations upgraded in Q2/Q3.
The first uncrewed landing demo tanker launch in Q3 with the landing demo in Q4.
Blue Origin Milestones:
New Glenn return to flight Q4 2026. First Blue Moon Mk1 landing in Q1 2027. Second Mk1 landing in Q4 2027 with the viper rover. Third Mk1 landing in Q1 2028 with an LTV (Lunar Terrain Vehicle) for Artemis 4.
Artemis 3 crew vehicle hardware complete in Q1 2027 with launch in Q2/Q3 2027.
LC36B (9x4 Pad) complete in Q3 2027 with the first NG 9x4 launch in Q4.
Source: ntrs.nasa.gov/api/citations/…
Enfin une timeline précise pour le hls de spacex et blue origin il etait temps !
Update on the HLS provider timelines from NASA
Short Overview:
Still targeting early 2028 for Artemis 4 and late 2028 for Artemis 5.
Starship cargo lander expected in 2032 and Mk2 cargo lander in 2033.
NASA provided an image of the CONOPS for Artemis 3 which is currently targeting NET Q3 2027.
Starship uncrewed landing demo still targeting NET Q4 2027. Blue Origin uncrewed Mk2 landing demo NET Q1 2028.
Starship Milestones:
First cape flight in Q4 2026 (currently NET Dec 10th). Completed HLS "Cabin 1" in Q4 2026 (ground testing cabin). This will have operations testing in Q1 2027 and airlock demonstrations in Q2.
Prop demo in Q1 2027, first launch from LC-37 also in 2027 - I personally believe 37a will be ready in Q2 or Q3.
Tank presurizations upgraded in Q2/Q3.
The first uncrewed landing demo tanker launch in Q3 with the landing demo in Q4.
Blue Origin Milestones:
New Glenn return to flight Q4 2026. First Blue Moon Mk1 landing in Q1 2027. Second Mk1 landing in Q4 2027 with the viper rover. Third Mk1 landing in Q1 2028 with an LTV (Lunar Terrain Vehicle) for Artemis 4.
Artemis 3 crew vehicle hardware complete in Q1 2027 with launch in Q2/Q3 2027.
LC36B (9x4 Pad) complete in Q3 2027 with the first NG 9x4 launch in Q4.
Source: ntrs.nasa.gov/api/citations/…
Andre🇨🇮 retweeted
"Launching at a high cadence requires a connected system - one that manufactures vehicles at scale, prepares customer payloads efficiently, supports reliable launch operations, and quickly returns reusable boosters to service. We are building that system here in Florida." Read more from our Senior Vice President of Operations Ian Richardson. bit.ly/4hRC0xe