The 1cFE initiative has finished
We set out to ask what would need to be true for fusion electricity to cost 1¢/kWh, and whether it could happen within a decade
Our answer: unlikely but not impossible, and vanishingly unlikely within ten years
1cf.energy/1cfe-completed/
Disclosure: @damienscott Tal Rubin are co-founders of Borealis Fusion, a p-B11 fusion company.
Astera Institute is an investor in Borealis Fusion.
The minimal-neutron study costs the class of machine Borealis is pursuing.
20
The publications, models and interactive tools remain available for others to use and extend.
We hope researchers and developers will test the assumptions, improve the models and examine approaches we did not study.
1cf.energy/outputs/
8
The two low-neutron cases cross one cent only at 3 GWe, with a 3% real cost of capital and plasma performance no device has shown.
At 7% real they rise to $14.6 and $18.4/MWh.
Plant size and financing decide whether they cross.
1cf.energy/corridor-findings…
7
The compact-learning corridor examines whether smaller units could reduce costs through faster iteration and repeated production.
The modeled path to one cent takes decades and requires buyers or support for expensive early units.
1cf.energy/compact-learning-…
7
The byproduct-value corridor examines heat, gold and synthetic fuel revenue.
Gold credits cut the electricity price a 1 GWe D-T plant needs by about $21/MWh, and to $17/MWh in the extrapolation case. Mercury supply and market depth set the limits.
1cf.energy/byproduct-value-c…
17
The minimal-neutron corridor examines a p-B11 magnetic mirror with no breeding blanket or tritium plant.
It reaches 2.6¢/kWh at 1 GWe with labeled extrapolations and 0.9¢ at 3 GWe under speculative assumptions, if the required burn can be achieved.
1cf.energy/minimal-neutron-c…
18
The direct-conversion corridor examines pulsed D-He3 fusion.
The costed 1 GWe plant reaches 2.7¢/kWh with labeled extrapolations and 1.1¢ with speculative ones, if energy recovery, helium-3 breeding and capacitor life deliver
1cf.energy/direct-conversion…
12
The pulsed-plant corridor examines cheaper drivers and the recurring expense of manufacturing a target for every shot.
The two laser-driven cases studied reach about 2.4 to 3.0¢/kWh under speculative assumptions.
1cf.energy/pulsed-plant-corr…
12
The most-mature corridor examines magnetic D-T plants.
In the selected 1 GWe stellarator case, cheaper components, shorter construction and favorable financing bring the speculative estimate to about 2.6¢/kWh.
1cf.energy/most-mature-corri…
15
From this broader work, we explored six candidate corridors to 1¢/kWh. Each starts with a premise about how fusion could become that cheap.
The studies examine selected designs and assumptions within these overlapping directions.
1cf.energy/six-candidate-cor…
14
Supported by @AsteraInstitute we built open-source costing tools and a research pipeline that examined a wide range of fusion concepts.
We evaluated how fuel, confinement, engineering, construction, operation and financing affect the cost of electricity.
35
Concept Explorer is now live as a hosted web app, no install required.
Compare 38 fusion concepts side by side, with cost breakdowns, sensitivities, and agentic research insights
concepts.1cf.energy
We built an automated pipeline that takes 38 fusion concepts, from tokamaks to exotic early-stage ideas, and turns each into a researched dossier, a cost model, and an LCOE estimate within a single framework.
42
Introducing 1costingFE: an open-source framework developed by 1cFE to estimate the cost of fusion electricity and explore paths to ultra-low-cost fusion. Give it a confinement concept, a fuel, and a design point, and it returns an LCOE with a full breakdown.
It covers 17 confinement concepts across magnetic, magneto-inertial, and inertial families, and all four major fuels (D-T, D-D, D-He3, p-B11). Including the aneutronic and direct-energy-conversion cases most fusion cost tools do not reach.
15
The code is open and small enough to read in an afternoon. Clone it, run the examples, and tell us where it is wrong. Reference cost data, account-level review, validation cases, and bug reports all welcome.
github.com/1cFE/1costingfe
13
The equations behind every cost account, the physics power balances, and the benchmarking against published reference designs are all in the methodology paper. A working draft, compiled from the same release the post describes.
files.1cf.energy/1costingfe_…
16
Want to feel the model first? The live explorer runs it in your browser.
Pick a concept and a fuel, drag the sliders, and watch the LCOE, the account breakdown, and the sensitivity tornado recompute as you go.
1costingfe-explorer.1cf.ener…
25
The full write-up: what 1costingFE is, what it does, and how to put your own numbers into it
1cfe.substack.com/introducin…