Paths to Progress is a $90 million transportation improvement program to rehabilitate, restore and enhance more than 60 roadway segments. #pavingLAroads
New Orleans, Louisiana
Joined March 2012
- Tweets646
- Following497
- Followers185
- Likes0
Permanent striping is underway on Franklin Ave. and is expected to be completed today. Travel lanes are open in both directions.
2
Traffic control is being removed on LB Landry Ave at this time. Both lanes in both directions are open,... fb.me/294gSVymq
Behrman Hwy. is open to traffic in both directions, including the newly striped cycle track. The status of... fb.me/7K68pViuM
Asphalt paving on Behrman Hwy. is complete. Permanent striping continues and the roadway has been reopened to... fb.me/4qJJqfPsl
Asphalt paving continues on Behrman Hwy. and should be completed this afternoon, weather permitting. Permanent... fb.me/4tG85GQB2
Asphalt paving is underway on Behrman Hwy. and will continue through this week. Travelers are reminded of the... fb.me/7F2GphKPr
Cold milling is underway on Behrman Hwy. and will continue through February 23. The milled material is being... fb.me/2Dhny4uMQ
Paths to Progress Program will host a neighborhood informational meeting to discuss upcoming repairs to Franklin... fb.me/2aalqHwvu
Construction of Old Behrman Highway and L B Landry Avenue is scheduled to start in 7 days.
#Algiers travelers... fb.me/7Uqs7oCeP
The anticipated start date for Old Behrman Highway and L B Landry Avenue road repairs is Monday, January 4.
The... fb.me/3r2LxhZKf
The anticipated start date for Old Behrman Highway and L B Landry Avenue road repairs is Monday, January 4.
The... fb.me/2iBqgLlPj
Construction of Old Behrman Highway (from Marr Avenue to LA 428) and L B Landry Avenue (from Mardi Gras Boulevard... fb.me/7TG890flu
Reminder: Tonight is our community informational meeting for Old Behrman Hwy and L B Landry Ave roadway repairs.... fb.me/4SGyHNZU5
Community meeting for the upcoming Old Behrman Highway and L B Landry Avenue road rehabilitation project is... fb.me/57soqGhR8
Paths to Progress will host a neighborhood informational meeting on Tuesday, December 1 at 6 p.m. The meeting... fb.me/7PPVlrADU
Road repairs to Old Behrman Highway (Marr Ave - LA 428) and LB Landry Avenue (Mardi Gras Blvd – Jefferson Parish... fb.me/4R6eeeeKH
Road repairs to Old Behrman Highway (Marr Ave - LA 428) and LB Landry Avenue (Mardi Gras Blvd – Jefferson Parish... fb.me/3dtgzYDV6
Construction is expected to start in December for the Old Behrman Highway (Marr Avenue - Behrman/LA 428) and LB... fb.me/21EwLe3Xf
Great infographic provided by DOTD that illustrates how projects go from conception to completion. fb.me/56nXYaBQa